Month: August 2016

Plastering Finished And Ceilings Up

The plasterers have finished their job and the ceilings are up. They still need to level them out and fit the all the cornicing.

20160830_17243720160830_172429 20160830_172447

Rendering finished and plastering has begun

The weather slowed the internal rendering but it was finished on Wednesday, 17/08/2016, and the wall plastering today, 22/08/2016.

20160816_173010 20160816_173336 20160816_173102 20160816_173014 20160822_16371020160822_16375420160822_16382120160822_16393620160822_163829

Roof Completed

The roof got installed on Friday, 5/8/2016. It comes together quite nicely with the bricks.

20160805_170932 20160805_170852 20160805_170752 20160805_170607 20160805_170504

Electrical, Gas, Water and Guttering Done

The electrical cabling, water and gas piping and the guttering has been completed.

20160803_172429 20160803_172348

20160803_171834

20160803_172124 20160803_172141

20160803_171943

The Colourbond roofing and insulation batts were delivered today as well. Fingers crossed the roof starts tomorrow.

20160804_165500

 