Paving is finished and the garage door is on

The paving is all finished and the site has been cleaned. The garage door has also been installed.

20161018_170909 20161018_170925 20161016_104357 20161018_165426 20161018_170901

Flooring, painting and appliances

Flooring has been installed by Trevor’s Carpets throughout the house. All external painting and touch-ups finished and the kitchen appliances have been installed. All that’s left is some brick paving and the garage door to be fitted!